COMING SOON: Rapid City Sports Complex

The Rapid City Sports Complex is on the way, and it’s designed to change the way Rapid City trains, competes, and plays.

Opening in late 2029 on the city’s north side, the indoor facility will bring eight basketball courts that convert into 16 volleyball courts, a hybrid turf area, sprint lanes, batting cages, a dedicated sports performance zone, and flexible event space together under one roof.

For Rapid City athletes, this means more opportunities to put in the work all year long. Local clubs, leagues, and teams will have access to reliable training and practice space through every season, giving athletes room to build skills, prepare for the next game, and keep competing when South Dakota weather moves practice indoors. From early morning workouts to evening practices and weekend competition, the complex will give local sports a year-round home built to keep Rapid City moving.

And when it’s time to welcome the competition, Rapid City will be ready. The complex will expand the city’s ability to host bigger brackets, more divisions, and tournament weekends that bring athletes and families from across the region to compete here.

This is more than a tournament facility. It’s a place for Rapid City athletes to train, grow, compete, and come back stronger season after season.

This page is your home court for the project. Follow construction progress, find answers to frequently asked questions, and explore resources for athletes, coaches, families, and event planners as the Rapid City Sports Complex comes to life.


 

FAQs


 

Timeline

April 2023: The process started with a study of what Rapid City had the opportunity to capture as a market. The Sports Commission, led by Domico Rodriguez, completed a feasibility study confirming community need and potential return.

June 2025: Rapid City announces Project Catalyst. Pete Lien & Sons commits a land donation on the city's north side for a publicly owned indoor sports complex.

Sept. 2, 2025: The Rapid City City Council approves the $125 million Destination District and $132 million Catalyst District TIF districts.

January 2026: Voters reject the neighboring Destination District (FKA Libertyland USA) TIF. The city reaffirms its commitment to the sports complex and begins reworking the funding and site plan.

April 2026: The city issues a request for proposals for architecture and engineering services.

July 2026: The Rapid City City Council approves the 22.65-acre land donation from Pete Lien & Sons, a professional facility management agreement, and an architecture and engineering agreement. Design work begins.

August 6, 2026: Sanford Health-Black Hills announced as the naming rights sponsor of the Sports Complex.

Next up: Final design and groundbreaking.

End of 2029: Target opening.

 

Questions or Concerns?

Misinformation can spread quickly on social media. If you have questions or concerns about the Rapid City Sports Complex, reach out to our team. We are committed to sharing clear, accurate information and keeping the community informed throughout every stage of the project.

Domico Rodriguez

Domico Rodriguez Executive Director of Rapid City Sports Commission

Grows Rapid City’s sports culture and boosts its economic impact. When he’s not working, he’s on the sidelines watching his kids' games, coaching, or officiating sports in the community.

Dig Deeper